SALIENT FEATURES OF PROJECT

Length of the Project Section 1 : 55.54 km
Section 2 : 8.152 = 7.902Km + 0.250 km (Shillong Approach)
Section 3 : 57.990 km (27.364 + 38.528 – 7.902)
Alignment & Lane Configuration Section 1 : Greenfield 4 – Lane (6 – lane Structure approach)
Section 2 : Widening of 4–Lane to 6–Lane
Section 3 : Improvement of 4/6 Lane
Completion Period 4 Years
Concession Period 30 Years
Concession Agreement Date 02.04.2025
Project Mode DBFOT (Toll)
Client National Highways Authority of India
Independent Engineer LASA (Lea Associates South Asia Private Ltd) in association with Alliance Engineers & Consultants
Topography Survey Bathymetric Survey & Traversing Section - 1 - Km 0+000 To 55+540 (Green Field) - 100% Completed Section - 2 - 163+237 to 171+000 (Widening) - 100% Completed Section - 3 – Improvement & Overlay - 100% Completed
Geo-technical Investigation Section - 1 - Drilling Completed - 196, Sample Dispatched – 191 – 86.43% Completed
Section - 2 - Drilling Completed - 31, Sample Dispatched – 31 – 100% Completed
Land for Infrastructure Development, PCY, Fab Yard etc. Section - 1 - 25+400, Kurua Village - Casting Yard for Bridge Well Foundation , Camp Office, Lab Mandakata - Crusher Plant Baihata - Fabrication Yard, RMC Plant, Lab, Mini Camp Laboratory Near Km 5+700 Baihata for testing of the Materials and Site Sampling.